Director of Engineering and Public Works Aaron Schrager presented a road work update at the Tuesday, October 7, Common Council meeting. His report included the following information from Union County and utilities on upcoming paving throughout Summit.
Union County
Union County will be paving Glenside Ave in the coming weeks as part of the county’s annual road paving program. Once the start date is finalized it will be shared on the city website and social media pages. Maps of the project plans are currently available on the county website.
NJ American Water
NJAW expects to complete repair work on infrastructure near the northern part of Morris Ave in the coming weeks. Following the completion of this work, paving on the following roads is expected to begin on November 3: Weaver St, Lincoln Ave, Madison Ave, Lowell Ave, Montrose Ave, Lafayette Ave, and Plain St.
Click to enlarge map

PSEG
PSEG work is ongoing throughout Summit and they will begin paving the following roads on October 27: portions of Springfield Ave, Evergreen Rd, Colonial Rd, Madison Ave, Miele Pl, Aubrey St, Lewis Ave, Beekman Rd, Ashland Rd, Pine Ridge Drive, and Baltusrol Pl.
Click to enlarge map

Director Schrager noted that utilities have been instructed that no work can take place on Halloween.
Additional project details and schedules will be shared on the city website and social media pages closer to the start dates.