This information has been updated as of Wednesday, November 5, 2025.
Please see below for the tentative schedule provided by PSE&G and JCP&L for upcoming milling and paving on several Summit streets, weather permitting and subject to change.
The affected roads will be closed during project work and for a few hours after paving is complete to allow the pavement to cure. Detours will be in place and police will be onsite to direct traffic. Residents should abide by all emergency "No Parking" signs.
All work will be performed between the hours of approx. 8AM and 5PM unless otherwise noted. Please note, limits are estimated and will be adjusted as needed in the field.
- Thursday 11/6/25
- NJAW Milling (8AM - 4PM): Weaver St
- Friday 11/7/25
- PSE&G Paving:
- 4:30AM - 4PM River Road intersections: at Lewis Ave, Plain St, and Miele Pl
- 7AM - 4PM Beekman from Cromwell Pkwy to High St
- 7AM - 4PM Ashland Rd from Manor Hill Rd to Mountain Ave
- 7AM - 4PM Baltusrol Pl from Baltusrol Rd to Hughes Pl
- NJAW Milling: Lafayette Ave, Lowell Ave, Montrose Ave
- NJAW Paving (8AM - 4PM): Weaver St
- Monday 11/10/25
- NJAW Milling: Lincoln Ave, Madison Ave
- NJAW Paving: Lafayette Ave, Lowell Ave, Montrose Ave
- Tuesday 11/11/25
- NJAW Paving: Lincoln Ave, Madison Ave
- NJAW Milling and Paving: Plain St (may be pushed to 11/12/25)
October 9, 2025, update:
Director of Engineering and Public Works Aaron Schrager presented a road work update at the Tuesday, October 7, Common Council meeting. His report included the following information from Union County and utilities on upcoming paving throughout Summit.
NJ American Water
NJAW expects to complete repair work on infrastructure near the northern part of Morris Ave in the coming weeks. Following the completion of this work, paving on the following roads is expected to begin on or about November 3: Weaver St, Lincoln Ave, Madison Ave, Lowell Ave, Montrose Ave, Lafayette Ave, and Plain St.
Click to enlarge map
PSEG
PSEG work is ongoing throughout Summit and they will begin paving the following roads on October 20 (delayed from October 16 due to poor weather conditions earlier in the week): portions of Springfield Ave, Evergreen Rd, Colonial Rd, Madison Ave, Miele Pl, Aubrey St, Lewis Ave, Beekman Rd, Ashland Rd, Pine Ridge Drive, and Baltusrol Pl. (Please note that this was originally scheduled for October 27 but PSEG moved the work to earlier to avoid Halloween and have hopefully more cooperative weather). As the city is not performing the work, these schedules are all subject to change.
Click to enlarge map

Director Schrager noted that utilities have been instructed that no work can take place on Halloween.
Union County
Union County will be paving Glenside Ave in the coming weeks as part of the county’s annual road paving program. Once the start date is finalized it will be shared on the city website and social media pages. Maps of the project plans are currently available on the county website.
*October 15 update: Union County paving of Glenside Ave will take place on Thursday 10/16 and Friday 10/17 between approx. 7AM - 4PM. Project details available here.
Additional project details and schedules will be shared on the city website and social media pages closer to the start dates.