Please see below for the tentative schedule provided by PSE&G for upcoming milling on several Summit streets, weather permitting and subject to change. Paving schedule to follow.
Road closures and detours will be in effect during project work and police will be onsite to direct traffic. Residents should park on neighboring side streets while roads are closed during project work.
All work will be completed between the hours of 8AM and 5PM.
Milling:
Friday 10/17/25
Lewis Ave from River Rd to Aubrey St
Aubrey St from Lewis Ave to Morris Ave
Plain St
Monday 10/20/25
Miele Pl from River Rd to Plain St
Evergreen Rd from Colonial Rd to dead end
Tuesday 10/21/25
Colonial Rd from Evergreen Rd to Kent Place Blvd
Madison Ave from Evergreen Rd to Kent Place Blvd
Beekman Rd from Cromwell Pkwy to High St
Ashland Rd between Linda Ln and Manor Hill Rd
Wednesday 10/22/25
Ashland Rd between Linda Ln and Manor Hill Rd
Thursday 10/23/25
Ashland Rd between Linda Ln and Manor Hill Rd
Baltusrol Pl from Baltusrol Rd to north of Hughes Pl
Monday 10/27/25 - Wednesday 10/29/25
Springfield Ave between Harrison Ct and Blackburn Rd
This information is available on the city website at cityofsummit.org/CivicAlerts.aspx?AID=2547.